CONSTRUCTION REPORT JULY 2020
AMPHITHEATRE
ARCH BACKSIDE
BLOCK A - DRAINAGE
BLOCK B - DRAINAGE
EXIT GATE
INTERNAL ROAD
LIFT CLADING
BLOCK A
WHAT IS COMPLETED?
Kitchen counter granite slab fixing work completed in the 6th series.
Electrical wiring work for 114 flats completed.
L2, L3 lift work under progress, L4 lift scaffolding work completed.
Tiling work 12 no's of MBR toilet completed.
6 no's of kitchen Dado tile rectification completed.
WHAT IS IN PROGRESS?
Fire door fixing is in-progress, total 10 no's fixed.
Granite cutting for sink fixing in kitchen and utility is in-progress in 4 flat side
Electrical wiring work in stair case 1,2,3 is under progress.
Expansion joint cutting work under progress.
UPVC window fixing under progress
Gas line work under progress for individual flat connection.
Touch up work for electrical points for individual flats under progress.
BLOCK B
WHAT IS COMPLETED?
Rainwater line packing and plastering work completed .
1st, 2nd, and 3rd-floor level ramp area and parking area with clubhouse masonry work completed .
08 number of flats flooring work completed .
50 number of toilet tile work completed .
35 number of utility work completed .
Lift (L5, L6 and L 7) cladding work completed from ground floor to 18th-floor level .
Amphitheater cladding, coping and nosing work (85%) completed .
55 number of kitchen counter slab completed .
59 Utility counter slab completed.
WHAT IS IN PROGRESS?
L5 and L6 vendor work in progress.
Corridor cable tray work under progress for electrical work .
Corridor rainwater pipeline erection work.
Corridor Handrail packing work under progress.
From the ground floor to UG sump, granite cutting work under progress.
External painting is in-progress.
Basement area electrical work is under progress.
Terrace level from mainline to sub plumbing line erection work under progress.
Electrical duct pipeline erection work under progress.
Backside road work under progress.
EXTERNAL WORK
WHAT IS COMPLETED?
Drain work completed in front of A block.
Recharge pit 10 nos completed.
Clubhouse shuttle badminton court fire fighting work completed.
Blockwork on the 3rd floor of the parking area of 1350 sft completed.
Blockwork of parapet wall from 2nd floor to 3rd ramp area completed towards A block (330sft).
Blockwork of parapet wall from 1st to 2nd floor, 2nd to 3rd floor Ramp area completed towards B block 660 sft.
2nd floor internal plastering work for parapet wall parking area of 1400 sft completed.
3rd floor parking area internal parapet wall plastering work 600 sft completed.
WHAT IS IN PROGRESS?
Electrical wiring work in progress.
Waterbody work in progress.
Road work started from the main gate to B block.
Waterbody granite cladding work in progress.
Amphitheatre granite cladding work in progress.
Fire fighting work of outer ring line is in-progress..