CONSTRUCTION REPORT APRIL 2020
BLOCK A
WHAT IS COMPLETED?
15th to 18th-floor tiling work completed in 4th series
Tiling work completed in 6th series
L2 lift cladding work completed in the ground to the 17th floor.
45 No's of Kitchen counter slab fixed at 6 series.
1st to 5th -floor ledge wall top slab fixing completed in 6 series.
1st to 5th -floor wash basin counter slab fixing completed in 6 series.
Ground floor mainline to panel room conduit work in progress at 6 flat series.
WHAT IS IN PROGRESS?
Ground floor granite flooring is in progress.
90% of the first coat of external painting work completed.
3rd coat putty work completed up to the 3rd floor.
Sandpaper applying work started at the 18th floor.
Windows lock and handle fixing in progress.
L1, L2, and L3 works in progress.
BLOCK B
WHAT IS COMPLETED?
7th-floor elevation concrete work (chejja) is completed
Toilets waterproofing work completed
Terrace maintenance slab work for overhead tank work completed
Handover of firefighting line is completed
WHAT IS IN PROGRESS?
From the ground floor to UG sump, granite cutting work under progress
External painting work started
Lift (L5) and (L6) were handover to Otis team and erection work under progress
Lift (L7 )and (L8) were handover to Mitsubishi team and erection work under progress
Basement area electrical work is under progress
Terrace level from mainline to sub plumbing line erection work under progress
Electrical duct pipeline erection work under progress
Backside road work under progress
East and north side pitching work under progress
Corridor cable tray work under progress for electrical work
Corridor rainwater pipeline erection work
Corridor Handrail packing work under progress
EXTERNAL WORK
WHAT IS COMPLETED?
Entrance gate plastering work completed
RCC compound wall completed near north west area
WHAT IS IN PROGRESS?
Plastering is in progress near the entrance gate area
South side, external storm water drainage RCC work is in progress
Wall cladding work in progress, near the entrance gate elevation
External Amenities work is in progress
External pitching levelling work is in-progress
External driveway area earth work progress for driveway construction purpose
Plastering progress for planting box