CONSTRUCTION REPORT December 2020

BLOCK A

What is completed?

    Concreting

  • Screed concrete at 4 flat series 4th floor below pergola
  • PCC for 2 no’s chamber at open to the sky, 3 no’s at the external chamber
  • 4 flat series GF lobby 100mm thick concrete for tiles laying
  • 6 flat series open to sky chamber to outside after pipe laying concrete
  • Flat no.301 & 306 balcony railing concrete

    Plastering

  • 6 flat series 1st to 8th floor all flats electrical DB box modification touchup work completed
  • 6 flat series 18th to GF corridor and staircase touchup work completed
  • 6 flat series 18th-floor non-customer flats door modification plastering completed
  • 1806 after electrical modification touchup completed
  • 1806 after door fixing gap packing and plastering completed
  • 4 flat series common area (staircase & corridor) GF to 3rd floor touchup work completed
  • 4 flat series 1st floor to 3rd floor plumbing pipe duct plastering completed
  • 4 flat series 4th to 18th floor all flats electrical and other all cement touchup works completed
  • 4 flat series GF parapet wall plastering completed
  • 4 flat series Ramp parapet wall pending plastering work from GF to 3rd floor completed
  • 4 and 6 flat series external touchup work at ducts, balcony, chajjas, and other plastering damage completed for dampness control
  • Commercial area GF south side base course plastering
  • Commercial area staircase backside wall plastering completed
  • DG room west side wall plastering completed
  • L3 & L4 lift call buttons fixing and finishing completed from GF to 18th floor
  • Terrace water tank manhole MS cover fixing and finishing 6 no’s completed
  • Commercial area GF toilet ventilator opening plastering completed for 2 no’s ventilator

    Blockwork

  • 6 flat series near STP entrance step block work and 4 flat series GF parking to lobby entrance block work completed
  • 6 flat series open to sky 2 no’s chamber, near STP 1 no’s chamber block work completed
  • 4 flat series 1st to 3rd floor plumbing pipe duct block work completed
  • DG room west side block work completed
  • Commercial area GF south side base course block work completed
  • Commercial area staircase backside blockwork up to beam bottom completed

    Blockwork

  • 6 flat series near STP entrance step block work and 4 flat series GF parking to lobby entrance block work completed
  • 6 flat series open to sky 2 no’s chamber, near STP 1 no’s chamber block work completed
  • 4 flat series 1st to 3rd floor plumbing pipe duct block work completed
  • DG room west side block work completed
  • Commercial area GF south side base course block work completed
  • Commercial area staircase backside blockwork up to beam bottom completed

    POP work

  • 6 flat series all floor flats POP touch up work completed
  • 6 flat series all floor corridor shaft door, staircase door touchup work completed
  • 4 flat series 18th to 13th floor all flats touchup work completed

    Tiles work

  • Customer flats 506, 507, 510, 604, 907, 1007, 1201, 1202, 1204, 1206, 1209, 1402, 1403, 1404, 1406, 1601, 1603, 1604, 1706, 1806 damage tiles removed and rectification completed,
  • 6 flat series After door fixing skirting work completed at 1206, 1302, 1403, 1404, 1406, 1601, 1603, 1604, 1706 and 1896.
  • 4 flat series 18th to 16th floor all flat toilet and utility damaged tile rectification work completed
  • Commercial area GF flooring tiles work completed and POP applied for damage safety
  • 4 flat series GF lobby flooring tiles work completed

    Granite work

  • L3 & L4 lift call button cutting from GF to 18th floor completed

    Paint and Primer

  • 6 flat series from 11th to 1st floor all non-customer flats sanding & primer completed
  • External duct 2nd coat painting completed at the east side, west side ducts completed from 1st to 18th floor, and Ramp area north side duct GF to 3rd floor 2nd coat paint completed
  • 6 flat series 5th to 18th floor corridor primer work completed, 10th to 18th floor corridor 1st coat paint completed, 5th to 9th floor corridor 2 coats putty completed,
  • 4 flat series 4th to 18th floor corridor primer work completed,
  • 4 flat series 4th, 17th and 16th floor all flats 3rd coat putty work completed, 4th and 17th floor all flats sanding, primer completed,
  • 6 flat series all flats door, window jambs putty and primer work completed

    Waterproofing Work

  • 301 & 306 west side balcony waterproofing completed

    Scaffolding work

  • Staging fixing and removing at flat no.3 duct from GF to 18th floor
  • Staging fixing at flat no. 1, 8 & 9 ducts from 3rd floor to 18th floor
  • Staging fixing at ramp area north side duct from GF to 3rd floor

    Electrical work

  • 6 flat series all customer flats switch box & switch plate fixing completed
  • 4 flat series all flats DP box adjustment work completed

    Lift

  • L1 & L2 all work completed by Mitsubishi
  • L3 & L4 work in progress by OTIS

    Spacewood door fixing

  • Door fixing completed at 1206, 1302, 1403, 1404, 1406, 1601, 1603, 1604, 1706, 1806
  • 1202 - Utility door and 1203 - main door fixing completed

    KBS false ceiling

  • 4flat series all 11 customer flats toilets False ceiling grid work completed
  • 6 flat series 4th floor corridor false ceiling work completed & floor no. 1, 2,3, 5,6 only corridor grid work completed. 7, 9, 10, 11, 12, 13, 14, 15, 16, 17 corridor grid marking and wall angle fixing work completed

    Fabrication

  • 4 flat series 9th floor MS platform work completed
  • Terrace both water tank MS staircase work completed
  • 606 balcony railing rectification work completed
  • 1206 balcony railing pending work completed

    Louvers fixing

  • 6 flat series flat no.1 & 3 west facing duct, flat no.9 series east-facing duct completed

    Gas pipe

  • 4 flat series all flats gas pipe and nozzle fixing completed

    Expansion joint work

  • 6 flat series 1st floor to 18th floor EPDM sheet fixing work completed
  • 6 flat series near-flat no.6 expansion joint external aluminum sheet fixing completed

    Broadband work

  • Airtel broadband work completed

What is in progress?

    Blockwork

  • 6 flat series GF DG shaft block work in progress

    Electrical work

  • 6 flat series all flats Internet cable wiring work in progress
  • 4 flat series all flats switch box fixing completed and switch plate fixing work in progress

    Lift

  • L3 & L4 work in progress by OTIS

    Zen Windows

  • 6 flat series Toilet ventilator glass fixing & silicon packing completed at all customer flats
  • 4 flat series all 11 customer flats toilet ventilator glass fixing and silicon packing work completed

    Broadband

  • Tatasky work in progress

BLOCK B

What is completed?

    Plastering / Masonry :

  • Fire shaft, plumbing shaft, communication shafts plastering work completed in 4th flat series and work completed in 6th flat series
  • Ground floor area masonry and plastering work completed
  • U G pump room and U G pump room staircase plastering work completed
  • 10th floor area masonry work completed near connecting bridge

    Tile work

  • 13 number of flats flooring tile work completed
  • 13 number of utility tile work completed
  • 30 Number of toilet tile work completed
  • 20 number of kitchen tile work completed
  • Commercial area 1st and 2nd floor flooring tile work completed

    Granite work

  • Ground floor staircase Granite work completed
  • Amphitheater cladding, coping, and nosing work (100%) completed
  • Amphitheatre pathway area 100% granite work completed
  • 24 number of kitchen counter slab completed
  • 15 toilet ledge wall top completed

    Concrete work

  • Balance Drain work concrete completed
  • 4th floor podium area screed concrete completed

    Fire fighting

  • 99% of overall fire fighting line work has been completed

    Paint and Primer

  • n customer flat's doors and windows jambs putty work completed
  • 4th flat series all flats windows jambs putty work completed

    Lift

  • Lift (L5) and (L6) work completed
  • (L7) Lift 95% Work completed
  • Lift (L8) 80% work completed

    Electrical work

  • All lift electrical work completed

    Scaffolding work

  • Most of the Scaffolding removing work completed

    Garden work

  • Near B Block, north side plain area planting work, near STP area pitching work completed
  • Opposite to commercial building planting work completed

    External

  • U G pump room work completed and pump room cleaning work completed
  • U g pump room plastering work completed
  • Amphitheater surrounding leveling work completed
  • Tennis and basketball area cleaning work completed
  • Garden maintenance work under process
  • B block South face 100% Drain top concrete completed

    Zen Windows

  • 200 frames fixed

    Shakti Hormann

  • Staircase, fire shafts, electrical and communication shaft doors work completed in 4th flats series

    Waterproofing work

  • 4th floor podium area Waterproof work completed

What is in progress?

    Lift

  • inspection work for both lifts

    Plumbing work

  • Along driveway area new plumbing line and inspection chamber work under process

    Material shifting

  • In 6th flat series excess and used materials removing and cleaning work under process

    External

  • Both the sides of B block driveway work under progress
  • Garden maintenance work under process

    Waterproofing work

  • U G sump tanks treatment work started
  • 5th floor clubhouse waterproofing work started

    clubhouse

  • 4th floor swimming pool waterproofing work completed and filling water for testing
  • Planter box cladding and coping work completed
  • All fire pipelines point work completed
  • 5th floor

  • 1. Planter box cladding and coping work completed
  • 2 . Media Room firework completed
  • 6th floor

  • 1.planter box cladding and coping work under progress
  • Waterproofing cleaning work completed