CONSTRUCTION REPORT January 2021

BLOCK A

What is completed?

    Plastering and masonry

  • 6 & 4 flat series, commercial area 100% plastering work completed

    Concrete work

  • 10th floor connecting bridge concrete completed
  • Terrace L4 lift LMR room screed concrete completed

    Tiles work

  • All tiles laying work 100% completed

    Granite work

  • All granite works 100% completed

    POP work

  • All customer flats touchup work completed
  • Door fixing touchup work completed for 60% flats

    Painting work

  • All customer flats up to 1st coat emulsion paint
  • Non-customer flats 1st coat paint completed for 30%flats
  • Commercial area primer work completed
  • Corridor and staircase putty work in completed for 50% flats
  • All MS works primer work completed

    Waterproofing work

  • All waterproofing works completed

    Acid wash & Grouting

  • All customer flats acid wash and grouting work completed

    Electrical work

  • All customer flats all electrical work completed

    Lift

  • L4 final installation work in progress 70% completed

    Zen Windows

  • 6 & 4 flat series all flats window fixing completed. silicon packing, hardware fixing, and glass fixing work completed 95%

    Spacewood door fixing

  • All customer flats door fixing work completed

    KBS false ceiling

  • All customer flats toilets false ceiling work completed

    Fabrication

  • Terrace floor all MS works completed

    Louvers fixing

  • 6 & 4 flat series work completed

    Gas pipe

  • 6 & 4 flat series all flats gas pipe and nozzle fixing completed

    Expansion joint work

  • 6 flat series 1st floor to 18th floor EPDM sheet fixing work completed

    Broadband work

  • Tatasky broadband work completed at shaft inside 4 & 6 flat series

What is in progress?

    Plastering and masonry

  • Final finishing and touchup work in progress

    Tiles work

  • only damage tile rectification and after door, fixing skirting work in progress

    POP work

  • Non-customer flats after door fixing touchup work in progress

    Painting work

  • Non-customer flats 1st coat paintwork in progress
  • Corridor and staircase putty work in progress
  • All MS works primer work completed

    Acid wash & Grouting

  • Non-customer flats in progress

    Electrical work

  • Non-customer flats DB connection work in progress

    Lift

  • L4 final installation work in progress

    Spacewood door fixing

  • Non-customer flats fixing work in progress

    KBS false ceiling

  • Non-customer flats toilet grid work completed only tiles fixing is pending
  • 6 flat series tiles fixing work in progress
  • 4 flat series corridor false ceiling grid work in progress

    Fabrication

  • 4th floor Flats window grill fixing work is pending

    Gas pipe

  • 6 & 4 flat series Meter fixing is pending

    Expansion joint work

  • aluminum plate fixing work in progress

    Fire fighting

  • All work completed by 95% only final fitting work in progress

BLOCK B

What is completed?

    Plastering

  • Fire shaft, plumbing shaft, communication shafts plastering work completed in 4th flat series and work completed in 6th flat series
  • Ground floor area Masonry and plastering work completed
  • U G pump room and U G pump room staircase plastering work completed
  • 10th floor area masonry work completed near connecting bridge

    Tile work

  • 13 flats flooring tile work completed
  • 13 utility tile work completed
  • 30 toilet tile work completed
  • 20 kitchen tile work completed
  • Commercial area 1st and 2nd-floor flooring tile work completed

    Granite work

  • Ground floor staircase Granite work completed
  • Amphitheater cladding, coping, and nosing work (100%) completed
  • Amphitheatre pathway area 100% granite work completed
  • 24 number of kitchen counter slab completed
  • 15 toilet ledge wall top completed
  • Cabal stonework at the entrance arch

    Concrete work

  • P C C for entry & exit area at the entrance arch
  • Concrete for a street light foundation
  • PCC for kerbstone work at driveway area
  • Balance Drain work concrete completed
  • 4th-floor podium area screed concrete completed

    Fire fighting

  • 99% of overall fire fighting line work has been completed

    Paint and Primer

  • In customer flat's doors and windows jambs putty work completed
  • 4th flat series all flats windows jambs putty work completed

    Lift

  • Lift (L5) and ( L6) work completed ready to move
  • ( L7)Lift Work completed ready to move
  • Lift (L8) 90% work completed
  • Inspection work completed in both the lift

    Electrical work

  • All lift electrical work completed

    Plumbing work

  • along driveway area new plumbing line and inspection chamber work completed except cover

    Scaffolding work

  • Most of the Scaffolding removing work completed

    Garden work

  • Near B Block, north side plain area planting work, near STP pitching area & plain area soil preparation for plantation
  • Opposite to commercial building planting work completed

    External

  • U G pump room work completed and pump room cleaning work completed
  • U g pump room plastering work completed
  • Amphitheater surrounding leveling work completed
  • Tennis and basketball area cleaning work completed
  • Cricket net practice play area civil work completed
  • B block South face 100% Drain top concrete completed

    Zen Windows

  • 200 frames fixed

    Shakti Hormann

  • Staircase, fire shafts, electrical and communication shaft doors work completed in 4th flats series

    Waterproofing work

  • U G sump tanks waterproofing work completed
  • 4th floor podium area Waterproof work completed

    Clubhouse

  • 4th, 5th, and 6th floor area irrigation work completed for plantation
  • At 4th floor pool area water leakage testing grouting work
  • Granite cladding work completed for Planter box at 4th, 5th& 6th floor area

What is in progress?

    Plastering

  • U G sump tanks plastering work under process
  • STP area inside plastering work under process

    Material shifting

  • In 6th flat series excess and used materials removing and cleaning work under process

    External

  • Along driveway area new plumbing line and inspection chamber work under process

    Material shifting

  • Both the sides of B block driveway work under progress
  • B block South face 100% Drain top concrete completed

    External

  • Both the sides of B block driveway work under progress
  • Garden maintenance work under process
  • B block South face 100% Drain top concrete completed

    Waterproofing work

  • STP tanks treatment work started
  • 5th floor clubhouse waterproofing work started

hidden