CONSTRUCTION REPORT November 2020

BLOCK A

What is completed?

    Plastering

  • 4 flat series electrical & communication shafts chipping & plastering as per dimension from 4th to 18th floor completed.
  • 4 flat series all 11 customer flats touchup works completed
  • 6 flat series GF near L2 lift block work plastering completed
  • 6 flat series all customer flats touchup works completed
  • Clubhouse backside external touchup from 5th to GF completed
  • Commercial area 1st & 2nd floor skirting touch up completed

    Blockwork

  • 4 flat series GF block work completed
  • 6 flat series GF near L2 lift block work completed up to the ceiling
  • Commercial area GF all-round 1-course block work completed

    Tiles work

  • 6 flat series 24 customer flats & 4th floor all flats tiles damage rectification completed
  • 4 flat series 11 customer flats tiles damage rectification completed
  • 6 flat series 501,703,802,1006,1201,1305 & 4 flat series 707,1009,1208 door skirting work completed
  • 4 & 6 flat series corridor area skirting work at the Main door, fire door, lift granite cladding area completed from 1st floor to 18th floor
  • 507 utility dado tiling completed as per customer modification.

    Concreting

  • 4th floor open to sky area between 4 & 6 series screed concrete completed
  • LMR 1 screed concrete completed

    Granite work

  • 4 flat series L4 wall cladding from GF to 18th floor completed
  • L3 wall cladding at only GF completed
  • L2 lift cabin granite flooring completed
  • 6 flat series all flats toilet wash basin counter hole cutting completed
  • 6 flat series L1 lift call buttonhole cutting from GF to 18th floor completed
  • Commercial area staircase GF flooring completed
  • 1004, 1007 kitchen window, Living area fixed window, Guest bedroom window sill level granite fixing completed.

    Paint and Primer

  • 6 flat series from 18th to 12th floor all flats sanding & primer completed
  • 6 flat series 501, 703, 802, 1006, 1201, 1206, 1305, 1402, 1403 ,1404, 1406, 1601, 1603, 1604, 1706, 1806 sanding, primer & 1st coat emulsion completed
  • External duct 2nd coat painting completed at flat no. 1, 3, 6, 8, 9 series from 1st floor to 18th floor
  • 4 flat series all 11 customer flats 3rd coat putty & primer completed (excluding 507 primer)

    Waterproofing Work

  • 4th-floor podium area towards clubhouse waterproof completed

    Scaffolding work

  • L4 lift inside scaffolding removing at GF & 1st floor, scaffolding jamming from 2nd floor and above completed

    Core cutting

  • 4 flat series all floors above communication & electrical shafts core cutting for electrical purpose completed

    Acid wash & Grouting

  • 6 flat series acid wash and grouting completed at 24 flats

    Electrical work

  • 4 flat series all customer flats switch box rectification work completed

    Plumbing work

  • 403 model flat sanitary fittings completed
  • 4th floor all 6 model flats grating fixing completed at toilets, utility & balcony

    Lift

  • L1 & L2 all work completed by Mitsubishi
  • L3 & L4 work in progress by OTIS

    Zen Windows

  • 6 flat series Toilet ventilator glass fixing completed at 1st to 5th floor all flats & 6th to 12th floor only customer flats
  • 6 flat series Silicon filling in windows, doors gap completed upto 12th-floor customer flats
  • 6 flat series upto 12th floor all customer flats sliding doors hardware completed
  • 6 flat series staircase window GF to 9th-floor silicon filling & hardware fixing completed
  • 4 flat series all 11 customer flats sliding door hardware fixing completed
  • 4 flat series 407, 707, 710, 910, 1007, 1008, 1010 living area sliding door refixing after tile damage rectification is completed

    Shakti Hormann

  • Communication & electrical shaft fire door fixing completed at 4 flat series from 1st to 18th floor completed
  • Commercial area rainwater shaft fire door fixing completed at 1st & 2nd floor completed

    Spacewood door fixing

  • Door fixing completed at 501, 703, 707, 802, 1006, 1009, 1201, 1208 & 1305

    KBS false ceiling

  • 4 flat series all 11 customer flats door gap POP packing completed
  • 4 flat series all customer flat toilets POP punning work completed
  • 6 flat series 4th-floor corridor false ceiling work completed & floor no. 1, 2,5,6 only corridor grid work completed

    Fabrication

  • 301 & 306 master bedroom balcony railings fixing completed
  • LMR room 1 & 2 doors, windows, and trap door fixing completed
  • L3 & L4 maintenance room door fixing completed
  • 4 flat series GF communication room door fixing completed
  • 10th floor near bridge parapet wall railing fixing completed

    Louvers fixing

  • 6 flat series flat no.1 & 3 series north-facing duct, flat no.6 series south-facing duct completed

    Gas pipe

  • 6 flat series all flats gas pipe and nozzle fixing completed

What is in progress?

    Plastering

  • Commercial area 1st & 2nd-floor Shaft chipping & plastering as per dimension
  • 4 flat series corridor & staircase touchup work from 4th to 18th floor
  • 4 flat series external touchup works at plumbing pipe inlet for dampness controlling at flats in progress
  • 4 flat series GF plastering work in progress

    Blockwork

  • 4 flat series 1st to 3rd-floor corridor area plumbing pipe all round block work in progress

    Concreting

  • Screed concrete at the 3rd-floor commercial area

    Electrical work

  • 6 flat series all customer flats switch box rectification & switch plate fixing in progress
  • 6 flat series all flats DP box adjustment work completed & 4 flat series work in progress

    Lift

  • L3 & L4 work in progress by OTIS

BLOCK B

What is completed?

    Plastering / Masonry :

  • Fire shaft, plumbing shaft, communication shafts plastering work completed in 4th flat series
  • Ground floor area Masonry and plastering work completed
  • U G pump room and U G pump room staircase plastering work completed
  • 10th-floor area masonry work completed near connecting bridge

    Tile work

  • All flats tile work completed
  • 13 Number of utility tile work completed
  • 30 Number of toilet tile work completed
  • 20 number of kitchen tile work completed
  • Commercial area 1st and 2nd-floor flooring tile work completed

    Granite work

  • Ground floor staircase Granite work completed
  • Amphitheater cladding, coping, and nosing work (100%) completed
  • Amphitheatre pathway area 100% granite work completed
  • 24 number of kitchen counter slab completed
  • 15 toilet ledge wall top completed

    Concrete work

  • Balance Drain work concrete completed

    Fire fighting

  • 98% of overall fire fighting line work has been completed

    Paint and Primer

  • In customer flat's doors and windows jambs putty work completed
  • 4th flat series all flats windows jambs putty work completed

    Lift

  • Lift (L5) and (L6) work completed ready to move
  • (L7) Lift 90% Work completed
  • Lift (L8) 80% work completed

    Electrical work

  • All lift electrical work completed

    Scaffolding work

  • Most of the Scaffolding removing work completed

    Garden work

  • Opposite to commercial building planting work completed

    External

  • U g pump room plastering work completed
  • Amphitheater surrounding leveling work completed
  • Tennis and basketball area cleaning work completed
  • B block South face 100% Drain top concrete completed

    Zen Windows

  • 210 frames fixed in B block

    Shakti Hormann

  • Staircase, fire shafts, electrical and communication shaft doors work completed in 4th flats series

    Waterproofing work

  • 4th-floor podium area Waterproof work completed

What is in progress?

    Plastering

  • Shaft doors plastering work under progress
  • Fire shaft, plumbing shaft, communication shafts plastering work under progress in 6th flat series

    Plumbing work

  • Along driveway area new plumbing line and inspection chamber work under process

    Material shifting

  • In 6th flat series excess and used materials removing and cleaning work under process

    Garden work

  • Near B Block, north side plain area planting work, near STP area pitching work under progress

    External

  • Both the sides of B block driveway work under progress
  • U G pump room work completed and pump cleaning work under process
  • Garden maintenance work under process

    Waterproofing work

  • U G sump tanks treatment work started
  • 5th-floor clubhouse waterproofing work started