CONSTRUCTION REPORT October 2020

BLOCK A

What is completed?

  • Shaft rectification plastering work completed
  • Touchup plastering work in staircase and flats
  • L1 lift machine room screed concrete.
  • DG and Extra slab screed concrete work
  • Miscellaneous touchup plastering important areas Corridor and lift Shafts
  • L1 lift Door Shaft internal granite side cement packing GF to 18 floor
  • Shaft chipping and grinding work
  • Cinders filling in commercial 3rd roof slab
  • Fire staircase and Shaft Door Fixing work completed
  • Customer flat toilet Grid ceiling 36 flats
  • 4th-floor corridor Grid ceiling work
  • Customer flats, staircase Doors gaps, and other touchup work
  • 24 customer flat skirting work completed
  • Customer 12 flats Doors gaps Marvello Plaster and corridor white cement touchup work
  • Customer flats 9th and 4th Model flats Internal 1st coat Emulsion work completed
  • 3 corridors external painting work completed from 5th floor to GF.
  • 4th floor Model flats and 302, 902 silicon filling, hardware Fixing, and alignment work completed.
  • 4th terrace - A6 and A4 series waterproof chipping cleaning completed
  • L4 Door both the side plastering GF to 18 floor
  • Shaft rectification plastering GF to 3rd floor
  • Chakkar plate fixed GF to 18 floor
  • Drainage Concrete work completed
  • Main Entrance curbstone laying work, Pond marking Dewatering completed.

What is in progress?

  • 28 flats Door Fixing work, 5% Architrave still in process.
  • L4 Lift Dodo block cladding work GF to 14th floor on process.

BLOCK B

What is completed?

  • Fire shaft, plumbing shaft, communication shafts plastering work completed in 4th flat series
  • Ground floor area 95% Masonry and plastering work completed
  • U G pump room staircase plastering work completed
  • 10th-floor area masonry work completed near connecting bridge
  • 13 number of flats flooring tile work completed
  • 13 number of utility tile work completed
  • 30 Number of toilet tile work completed
  • 20 number of kitchen tile work completed
  • Commercial area 1st and 2nd-floor flooring tile work completed
  • Ground floor staircase granite work completed.
  • Amphitheater cladding, coping, and nosing work (100%) completed
  • Amphitheatre pathway area 70% granite work completed
  • 20 number of kitchen counter slab completed
  • 35 Utility counter slab completed
  • 15 toilet ledge wall top completed
  • 28 toilet hand wash counter slab fixed
  • U G Pump room area floor screed and saucer drain work completed
  • 97% of overall fire fighting line work has been completed
  • All lift electrical work completed
  • (L7) Lift 80% Work completed
  • (L8) Lift 70% work completed
  • UG pump room plastering work completed
  • Amphitheater surrounding leveling work completed
  • Tennis and basketball area cleaning work completed
  • B block South face 100% Drain top concrete completed
  • 97% drain work completed
  • 4th-floor podium area Waterproof work 40% completed
  • 50% Zen Windows fixing completed in customer flats.
  • Staircase and fire shafts doors completed in 4th series.
  • Drain work 100%completed
  • Front gate planter box curb stonework is completed
  • Cobblestone and pond marking work
  • External water drawstring work and prepare road base, recharge pit work is completed

What is in progress?

  • Doors and windows jambs putty work under process
  • Lift (L5) and (L6) work completed, Inspection work under process from Safety team
  • Yet to start inspection work in both the lift
  • Along driveway area new plumbing line and inspection chamber work under process
  • In 6th flat series excess and used materials removing and cleaning work under process
  • Scaffolding removing under process in Clubhouse 4th floor and 1st floor to 3rd floor for parapet wall in A, B, C blocks
  • Near B Block, north side plain area planting work under progress
  • Both the sides of B block driveway work under progress
  • U G sump room and pump cleaning work under process
  • Garden maintenance work under process
  • U G sump tanks treatment work started
  • 04pits are pending at the marketing office Area.